For a project, it takes 6 days for Party A to complete and 10 days for Party B to complete

For a project, it takes 6 days for Party A to complete and 10 days for Party B to complete


For a project, it takes 6 days for Party A to complete and 10 days for Party B to complete
1/6:1/10=5:3



For a project, it takes 6 days for Party A to complete and 10 days for Party B to complete______ What is the efficiency ratio of a to B______ .


The ratio of working time is 6:10 = 3:5, and the ratio of working efficiency is 10:6 = 5:3