To build a road, team a needs 20 days to build it alone, and team B needs 30 days to build it alone. Now team a and team B work together for several days, and team B has another task, It took 18 days to build the road. How many days did Team B build it
(1-1/20×18)÷(1/20-1/30)
=1/10÷1/60
=6 days
To build a road, it takes 20 days for Party A to build it alone, and 30 days for Party B to build it alone. Now, after several days of joint construction by Party A and Party B, team B transfers out. It took 18 days to build the road. How many days did Team B build it?
(1-120 × 18) / - 130, = (1-910) / - 130, = 110 × 30, = 3 (days). A: Team B repaired it for 3 days
RELATED INFORMATIONS
- 1. For a section of highway, the original plan was that team a and team B would build it together in 20 days. In fact, team a would build it 12 days first, then team B would join team a for 13 days, and team B would build the rest in 3 days. How many days would it take for team a and team B to build this section of highway separately?
- 2. Team a and team B built a road together. When they finished the task, team a built 815% of the road. If team B finished it alone in 24 days, how many days did team a finish it alone? (Qingshan District, Wuhan City)
- 3. Team a and team B work together to build a road. When completing the task, team a builds 15 / 8 of the road. If team B works alone, it will take 24 days, and team a works alone, how many days
- 4. For a section of highway, it will take 15 days for engineering team a alone, 20 days for engineering team B alone, and there are 2600 meters left after 3 days of construction by both teams. How many meters are there in this section of highway?
- 5. It will take 15 days for team a to build a road, 12 days for team B to build it alone, six days for team a to build it first, and the rest will be jointly built by team a and team B. how many days will it take for team a and team B to build it together?
- 6. Team a and team B work together to build a 240 km long road. Team a works alone for 10 days, and a pair works alone for 15 days. How many days will the two teams work together? There are two solutions,
- 7. There are 120 people in the two engineering teams, of which the number of team B is three times less than that of team A. how many people are there in each team?
- 8. Two cars set out from a certain place at the same time to transport a batch of goods to the construction site 165 kilometers away. Car a arrived 48 minutes earlier than car B. when car a arrived, car B was 24 kilometers away from the construction site. How many hours did car a spend on the whole journey?
- 9. Two cars set out from a certain place at the same time to transport a batch of goods to the construction site 165 kilometers away. Car a arrived 18 minutes earlier than car B. when car a arrived, car B returned
- 10. Two cars set out from a certain place at the same time to transport a batch of goods to the construction site 160 kilometers away. Car a arrived 0.8 hours earlier than car B, Two cars set out from a certain place at the same time to transport a batch of goods to the construction site 160 km away. Car a arrived 48 minutes earlier than car B. when car a arrived at the destination, car B was 24 km away from the destination. How many hours did car a spend on the whole journey?
- 11. A highway was originally planned to be completed by 120 people in 50 days, and 20 people were transferred after 30 days. The remaining people need to work a few more days than the original plan
- 12. A road construction team is going to build a section of expressway. Team a will finish it in 100 days, and team B will finish it in 150 days. Now the two teams are working together. During this period, team a has a rest for 8 days, while team B has a rest After that, I had a 13 day rest (two teams can't rest at the same time). How many days did it take from construction to completion Don't solve the equation
- 13. The original number ratio of team a and team B is 7:3. After some people are transferred from team a, the number ratio of team a and team B is 3:2. Team B has 120 people. How many people are there in team B?
- 14. The original number ratio of team a and team B was 7:3. After some people were transferred from team a to team B, the number ratio of team a and team B was 3:2. Team B now has 120 people, and team B has 120 people
- 15. Team a and team B built a road. Team a built two fifths of the road, team B built the remaining two thirds, and team B built several parts of the road Make it up later What percentage of the road has team B built? right off! It's urgent!
- 16. The number of class A in a school is five more than two-thirds of class C. if 10 people from Class A are transferred to class C, class C will work twice as much overtime How many people are there in each class
- 17. Two groups of students go to plant trees. The ratio of group A to group B is 5:3. If 10 people are transferred from group A to group B, the ratio of group A to group B is 5:4 people
- 18. There are 84 students in class A and class B, 57 students in 5 / 8 of class A and 3 / 4 of class B
- 19. In the workshop a and B, the ratio of the original number of workers is 2:3, and Party A transfers 70 workers. At this time, Party B is 4 / 9 of that of Party A, and how many workers are there?
- 20. The ratio of class A to class B is 4|1. If 10 students are transferred from Class A to class B, the ratio of class A to class B becomes 7|2. How many students are there in each class?