The diameter of the circular pipe conveying concrete in the construction site is 10 cm. The velocity of concrete in the pipe is 35 meters per minute. A truck of concrete has 7 cubic meters, How many minutes can the whole delivery be completed? (the number obtained shall be kept to one decimal place)

The diameter of the circular pipe conveying concrete in the construction site is 10 cm. The velocity of concrete in the pipe is 35 meters per minute. A truck of concrete has 7 cubic meters, How many minutes can the whole delivery be completed? (the number obtained shall be kept to one decimal place)

10cm = 0.1M
(0.1 △ 2) &# 178; × 3.14 = 0.0785 (M2)
0785 × 35 = 2.7475 (M3)
7 △ 2.7475 ≈ 2.5 (min)
A: only 2.5 points can complete the transportation