If 180 bags of cement are to be transported to a construction site every day, it will take 40 days. Now it will take 25 days to complete the transportation, how many bags should be transported every day?

If 180 bags of cement are to be transported to a construction site every day, it will take 40 days. Now it will take 25 days to complete the transportation, how many bags should be transported every day?


X bags should be delivered every day
180:X=25:40
25X=180*40
25X=7200
X=7200/25
X=288
288 bags a day