There is a practical problem. It's actually very simple. It's about engineering problems The efficiency of team a is 3 / 5 of that of team B. the two teams can complete 2 / 3 of this section of road in 6 days. The rest will be completed by team B alone. How many days will it take to complete it?

There is a practical problem. It's actually very simple. It's about engineering problems The efficiency of team a is 3 / 5 of that of team B. the two teams can complete 2 / 3 of this section of road in 6 days. The rest will be completed by team B alone. How many days will it take to complete it?


The efficiency of team a is 3 / 5 of that of team B. Team B completes two-thirds of the road in six days. Team B will finish the rest of the road by itself. How many days will it take to finish it? Team B cooperates in six days to finish it: 2 / 3, team B cooperates in one day: 2 / 3 / 6 = 1 / 9, so team B's efficiency is: 1 /